BAKU, Azerbaijan, November 4. In the first
three quarters of 2026, Azerbaijan’s Azeri-Chirag-Gunashli (ACG)
block of fields drilled and completed 12 oil producer, three water
injector and two gas injector wells, says the latest report by
bp.
The company said that one of the oil producer wells – D18Z,
drilled from the East Azeri platform, marked a significant
milestone for ACG.
“The well achieved over 2,000 metres of open hole, including
more than 1,500 metres of sand within the target reservoir, giving
it the most extensive reservoir contact of any ACG well drilled to
date. This achievement highlights how advanced seismic imaging,
drilling and completion technologies are helping maximize recovery
and sustain long-term production from the mature ACG field,” said
bp.
The report reveals that total ACG production for the first three
quarters of 2026 was on average about 320,000 barrels per day (b/d)
(about 87 million barrels or 12 million tonnes in total) from the
Chirag (18,800 b/d), Central Azeri (84,600 b/d), West Azeri (72,000
b/d), East Azeri (45,700 b/d), Deepwater Gunashli (46,700 b/d),
West Chirag (25,300 b/d) and ACE (26,900 b/d) platforms.
BP Exploration (Caspian Sea) Limited is the operator on behalf
of the Contractor Parties to the ACG Production Sharing
Agreement.
ACG participating interests are: bp (operator - 30.37%), SOCAR
(35.30%), MOL (9.57%), INPEX (9.31%), ExxonMobil (6.79%), TPAO
(5.73%), ONGC Videsh (2.92%).